Supply and Installation of LPS at Shalbahan Farms Ltd. U-2

Project Title:Supply and Installation of Lightning Protection System based on NFPA780 & BNBC Standard. Client: Shalbahan Farms Ltd. Unit-2 (Paragon Group) Location: Kaliakoir, Mouchak, Gazipur Project Duration: Jan, 2026 to Mar, 2026 Project Value:3.50 Million BDT (With Earthing System). Scope of Work:Supply, installation, testing, and commissioning of conventional lightning protection system for entire factory complex. Approximate 2 thousand...

Arla Foods Bangladesh Ltd. - Earthing System

Project Title:Supply and Installation of Conventional Earthing System as per BNBC Standard. Client: Arla Foods Bangladesh Ltd. Location: Jailkhana Road, Konabari, Gazipur Project Duration: June, 2022 to August, 2025 Project Value:12.70 Million BDT. Scope of Work:Supply, installation, testing, and commissioning of conventional earthing system for entire factory complex. 65 set of 350 feet depth earthing system was...